The initial order for this roof at Wollongong University was for 34–metre sheets of Speed Deck Ultra® concealed fixed decking. However, long trucks were unable to access the site. In addition, power lines and trees 20 metres high prevented a crane from reaching over to the site from the road.

The solution was to break the roof run into two 17-metre sheets connected with the Stramit FarLap® roof lap joint system. This allowed the use of a shorter truck and a smaller crane.

The innovative Stramit FarLap® roof lap joint system allows long decking runs to be broken into shorter sheets that can be lapped, without the need for conventional stepped joints. The FarLap® unit provides a combination of a strong joint and a weather resisting seal between lapped sheets of Stramit Speed Deck Ultra® concealed fixed decking.

As well as simplifying and speeding the installation, the solution also improved site safety, providing lighter, shorter sheets that were easier to handle, and a lighter pack mass.

Acknowledgements

Source
:

Stramit - 2012

Project
:

University of Wollongong, Building 1

Builder
:

Ichor Constructions

Roofing Contractor
:

Rise Above Roofing Services

Not all products featured in this case study are suitable for every application, project and environment. You should confirm the suitability of particular products for your project by contacting the supplier directly and by obtaining information and advice specific to your circumstances. The statements, information and opinions quoted in this case study are provided by the featured supplier and reflect the views of the author, not BlueScope Steel Limited. BlueScope Steel Limited is not responsible or liable for any such content. Please refer to the Terms of Use for further details.